ROCK
CREEK DAM RETROFIT PROJECT

2008
Presently, Davis Hydro has allowed all FERC permits to expire as PG&E
has not yet come to final agreement on the proposed MOU. We have worked
with PG&E to develop the project as contract employees or as third
party developers. The request to privately develop the project either
inside their dam or the right apron remains waiting on PG&E for a
go ahead. Copies the MOU were included in later FERC Progress Reports.
November
2007
Current Status:
PG&E has stopped progress on this project for undisclosed reasons.
They have given us complete support and reassurances up to 2 years ago
this month at which time we were negotiating a final MOU. Then suddenly
no further communication and calls were not returned. At this point PG&E
has filed for a preliminary
permit on the site. We remain willing to do the project with them.
Progress: November 2006
1st Stage Consultation is complete; studies continue. We paid over $10,000
to PG&E to approve the interconnection. Now awaiting PG&E's time
for review of designs and possible lease agreements.
Progress: October 2006
A draft MOU submitted in November 2005 is being reviewed
by PG&E. We have been waiting for PG&E to finish their review.
We are actively working with CFG to finish the Stage 1 studies. We anticipate
draft completion of these studies by December, 2006. There have been on
hold pending completion of PG&E's review.
The most recent FERC Progress Report is available here
as a MS Word 200 formatted document.
Past progress and activity reports with associated
documents are available, please visit
here.
PG&E has been reviewing an agreement submitted in November
2005 on this project. No decision has been made. Informal
discussions have suggested that PG&E feels that there might be interference
with their current operations. Davis Hydro has requested discussion
of the project, but for the past year and a half PG&E has been unable
to schedule this meeting.
Related Ongoing Projects
Sediment Transport: Ongoing discussions
are taking place on how to use the hydro project to help with downstream
sediment transport between storms. To that end, Davis Hydro has prepared
a white paper with some discussion ideas that might be considered if
the current strategy proved insufficient to keep the gate inlets clear.
This white paper, dated (9/14/04) is available for download
here.
A related technical discussion paper dated September 2004
is available
here.
Communication: One of the benefits of
the hydro power will be a the offer of an improvement in communication
with, and control of, the dam using new communication technology, control,
and flow instrumentation. This system will use an Internet based, non-proprietary,
high security, satellite-based communications system. This satellite-based
system is suggested as a direction for system growth that can be incrementally
expanded to all PG&E dams.
Ramp Rate Control: To control ramp rates
a small amount of additional equipment is suggested that could be controlled
in different ways. The improved flow instrumentation and control options
(not communication) are addressed in a white paper written (9/16/04).
This is available for download here.
In early May, we filed our first progress report of the
Preliminary Permit with the FERC and the California State Water Resources
Control Board. A MS WORD copy is available here
(5/10/05).
(Updated on 2-4-05)
This is updated irregularly as people ask to join, leave, or addresses
change.
Davis hydro
is interested in your comments, and whether you want to receive future
notices. If so, please E-mail here,
and you will be added to our E-mailing list.
|